How Much Does Planning Permission Cost in 2026?

The headline answer: in England, the council fee for a householder planning application for an extension or alteration to a house is £548 (fees from 1 April 2026). But the application fee is only one part of what it costs to get permission and get ready to build.

Here’s what to budget for.

Planning application fees in England

Fees are set nationally and are the same at every council in England. These are the fees most relevant to homeowners, from 1 April 2026:

Application Fee
Householder application (extension or alteration to one house) £548
Householder application (two or more houses, or flats) £1,083
Prior approval for a larger single-storey rear extension £249
Lawful development certificate (proposed work) Half the normal planning fee, so £274 for a typical householder project
Full application for one new house £610
Approval of details to discharge conditions (householder) £89
Non-material amendment (householder) £46

Source: Planning Portal fee schedule, England, from 1 April 2026. The Planning Portal also adds a service charge if you submit your application through its website.

Two points worth knowing:

  • A refusal means paying again. If an application is refused and you submit a revised one, a new fee is usually due. Getting the design and drawings right first time saves money.
  • Not every project needs a planning application. Many extensions and loft conversions fall within permitted development. A lawful development certificate confirms this for half the fee.

Drawings and design

For most projects, the drawings are the largest part of the cost of getting permission. A planning application needs, at minimum, existing and proposed floor plans and elevations, plus a site location plan and block plan. Many applications also need sections and a design statement.

The cost depends on the size and complexity of the project, so it’s worth getting a fixed quote that sets out exactly which drawings are included. Check whether the quote covers:

  • the measured survey of your house
  • planning drawings and the submission itself
  • responding to any council queries during the application
  • building regulations drawings, which you’ll need next

Surveys and reports

Some projects need extra information before the council will accept the application:

  • Measured survey. An accurate survey of the existing house is the starting point for good drawings.
  • Tree survey. Often needed if work is near protected trees or trees in a conservation area.
  • Flood risk assessment. Needed for extensions in some flood zones.
  • Ecology or bat survey. Sometimes needed for loft conversions and roof work, because bats are a protected species.
  • Heritage statement. Needed in conservation areas and for listed buildings.

Our Project Checker will flag whether your address falls in a conservation area, flood zone or other constraint that’s likely to need extra reports.

Pre-application advice

Many councils offer pre-application advice, where a planning officer gives an informal view before you apply. Fees and services vary by council. It can be worthwhile for larger or more sensitive projects, but most straightforward extensions don’t need it.

Costs after planning permission

Permission is not the end of the paperwork. Before building, most projects also need:

  • Building regulations approval. Building control charges a fee, which varies by council or approver and by the size of the work. You’ll also need building regulations drawings.
  • Structural engineer. Calculations for beams, foundations and other structural work.
  • Party wall costs. If you’re building on or near a shared wall, the Party Wall etc. Act 1996 may apply, which can mean surveyor’s fees.

Budgeting tips

  • Budget for the whole process, not just the fee. Drawings, surveys and building control usually cost far more than the council fee itself.
  • Check the route first. If your project falls within permitted development, the cost and the wait are both lower.
  • Get it right first time. A refusal costs a second fee and months of time.